Sl. No. Ward No Name of the Work Source of Finance Estimated Project Cost(in lakhs) Date of tender Name of the Contractor Start date Completion Date (as per aggrement) Expected Date of Completion Physical Progress Payment made Payment pending Bills ready for payment after all scrutinyl Photograph
1

Construction of storm water Drain from Kombettu College Road to Haradi Road

IDSMT 6.05 Lakhs 17.03.06 P.V.Usman 6.07.06 6.09.06 15.09.06 Earth work is in progress

 

- - -
2 25

Construction of new minor bridge at Bhatti Vinayaka Temple road Balnad (27th ward)

Municipal 3.50 Lakhs 25.03.06 M.N.Prabhakar 15.04.06 - - Concrete cement bed and Abutment work completed - - -
3 20

Development of the Mahalinga Pai layout road

Municipal 1.50 Lakhs 2.12.05 P.A.Usman 15.06.06 - - Drain work and one layer mettaling work completed

 

- - -