Puttur Town Municipal Council
Ward Woks
| Sl. No. | Ward No | Name of the Work | Source of Finance | Estimated Project Cost(in lakhs) | Date of tender | Name of the Contractor | Start date | Completion Date (as per aggrement) | Expected Date of Completion | Physical Progress | Payment made | Payment pending | Bills ready for payment after all scrutinyl | Photograph | ||
| 1 |
Construction of storm water Drain from Kombettu College Road to Haradi Road |
IDSMT | 6.05 Lakhs | 17.03.06 | P.V.Usman | 6.07.06 | 6.09.06 | 15.09.06 |
Earth work is in progress
|
- | - | - |
![]() |
![]() |
![]() |
|
| 2 | 25 |
Construction of new minor bridge at Bhatti Vinayaka Temple road Balnad (27th ward) |
Municipal | 3.50 Lakhs | 25.03.06 | M.N.Prabhakar | 15.04.06 | - | - | Concrete cement bed and Abutment work completed | - | - | - |
![]() |
![]() |
![]() |
| 3 | 20 |
Development of the Mahalinga Pai layout road |
Municipal | 1.50 Lakhs | 2.12.05 | P.A.Usman | 15.06.06 | - | - |
Drain work and one layer mettaling work completed
|
- | - | - |
![]() |
||